英语翻译烟台天鸿时代广场基坑支护结构设计与施工摘要:[摘 要]基坑开挖后,对基坑进行必要的支护,对工程的顺利施工起着非常重要的作用.本工程中,通过对土压力的计算,对周围环境的研

来源:学生作业帮助网 编辑:作业帮 时间:2024/05/04 04:56:52

英语翻译
烟台天鸿时代广场基坑支护结构设计与施工
摘要:[摘 要]
基坑开挖后,对基坑进行必要的支护,对工程的顺利施工起着非常重要的作
用.本工程中,通过对土压力的计算,对周围环境的研究,决定采用锚杆加排桩的支护方式.施工过程中,监测不可缺少,现场监测有助于及时发现可能发生危险的先兆,判断工程的安全性,防止工程破坏事故的发生,以便采取必要的工程措施;以监测的结果指导现场施工,进行信息化反馈优化设计,使设计达到优质、安全.烟台地区地下水位较浅,还要采取降水和其他必要措施以保证施工过程中不会出现涌水、流砂及其引起的地面沉陷.

Topic :Yantai Tianhong Times Square Excavations Design and Construction
After the excavation of the pit to conduct the necessary support to the smooth construction of the project played a very important role.The project,a pair of earth pressure through the calculation of environmental studies to determine bolt increase pile supporting patterns.Construction process,not a lack of monitoring,on-site monitoring to detect possible danger signs,judgment of the security,to prevent damaged incidents,in order to take the necessary measures to the project; The results of the monitoring to the scene to guide the construction,information feedback optimization of the design,to make it possible to design high-quality,and safety.Yantai shallow groundwater,precipitation and also take other necessary measures to ensure that the construction process will not be gushing water.flow of sand and ground subsidence.

After structure excavation, carries on essential to the hole excavatedfor building foundation 支护, smoothly constructs to the projectcount for much making With. In this project, through to the earth pr...

全部展开

After structure excavation, carries on essential to the hole excavatedfor building foundation 支护, smoothly constructs to the projectcount for much making With. In this project, through to the earth pressure thecomputation, to the environment research, decided uses the anchor rodto add 排桩 支护 the way. In the construction process, monitorsessentially, the scene monitor is helpful to the prompt discoverypossibly has the dangerous omen, the judgement project security,prevents the project destruction accident the occurrence, in order totakes the essential project measure; Monitors the result instructs thescene construction, carries on the information feedback optimizationdesign, enables the design to achieve high quality, is safe. TheYantai area subsoil water level is shallower, but also must adopt theprecipitation and other essential measures guaranteed in theconstruction process cannot appear wells up the ground settlementwhich the water, the shifting sand and its causes.

收起